How a pool gets built

Ten stages with honest week ranges, the things that slow a build down, and the decisions you make along the way.

From first visit to first swim

The ten stages

Week by week

  1. Stage 01 · Week 0

    Design consult

    We meet at your home, walk the yard, talk about how you will use the pool and give you an honest first range.

  2. Stage 02 · 1 to 3 weeks

    3D design and proposal

    Survey, sun study and a 3D design with two rounds of changes. Then a written proposal with every line priced.

  3. Stage 03 · 2 to 6 weeks

    Contract, engineering and permits

    Engineered plans go to your city (and HOA, which can add 2 to 4 weeks). We handle the forms and the follow-up.

  4. Stage 04 · 2 to 5 days

    Layout and excavation

    We paint the shape on the ground and walk it with you before digging. Rock can add days; you hear about it the same day.

    Two builders in hard hats and safety vests point across a backyard marked out for a new pool
    Layout day: the shape is painted on the ground and walked with you before any digging.
  5. Stage 05 · 1 to 2 weeks

    Steel and plumbing

    Rebar cage, plumbing lines and electrical bonding. The city inspects before any concrete is placed.

  6. Stage 06 · 1 day, then 7 to 10 days

    Gunite shoot and cure

    The shell is sprayed in one day, then watered daily while it cures. Fiberglass pools are set by crane here instead.

    A crew member sprays gunite over the steel rebar cage of a curved pool
    Shoot day: gunite goes on over the steel in a single day. Fiberglass shells are set by crane instead.
  7. Stage 07 · 2 to 3 weeks

    Tile, coping and decking

    Waterline tile, coping and the deck. Outdoor living work usually runs at the same time.

  8. Stage 08 · 1 to 2 weeks

    Equipment, electrical and barrier

    Pump, filter, heater and controls are set. Fence, gates and door alarms go in and are inspected.

  9. Stage 09 · 2 to 4 days

    Interior finish and fill

    The finish goes on and the pool fills the same day. Keep the hose running; it takes 1 to 2 days.

  10. Stage 10 · 2 weeks

    Start-up and pool school

    We balance the water, brush the new finish and teach you the equipment, the chemistry and the safety plan.

What slows a build down

No builder controls the weather or the bedrock. What we control is how fast you hear about it. Every delay gets a call the same day and a line in the Friday update.

  • 01

    Rain

    We cannot dig, shoot or pour in heavy rain, and a soaked hole needs time to drain. Expect a few rain days in spring and fall.

  • 02

    Rock

    Limestone is common west of MoPac. It slows digging and is billed at the per-load rate in your contract. You get photos the same day.

  • 03

    Permit and HOA queues

    Some cities turn permits around in two weeks, others in six. HOA boards often meet monthly. We submit the day plans are ready.

  • 04

    Changes mid-build

    Changing the tile or adding a feature is fine, but each change is a written change order with its own price and days.

  • 05

    Material lead times

    Popular fiberglass shells, heaters and some tiles can have waits in spring. We order early and tell you the dates.

  • 06

    Inspections

    Each inspection needs a city slot. Most come within two or three days; we book them as soon as the work is ready.

Decisions, and when they are due

Late choices are the delays we can avoid together. Here is when we will ask.

Before you sign
Pool shape, size, depth, features and the barrier plan
Before excavation
Equipment location and where the dirt and machines go
By the end of steel
Waterline tile, coping and interior finish colors
Before decking
Deck material, color and drainage
Before start-up
Who in the family attends pool school

The Friday update

Every Friday of your build, Grant sends photos and four lines: what got done, what is next, anything that slipped, and anything we need from you. If nothing happened that week, he says so.

  • One superintendent from dig to start-up
  • Same-day call for rock, rain or a failed inspection
  • Payments due only when a stage is finished

Permits and inspections explained

Want a start date you can plan around?

At your design consult we check permit queues for your city and shell stock, then give you an honest window for your first swim.