How a pool gets built
Ten stages with honest week ranges, the things that slow a build down, and the decisions you make along the way.
From first visit to first swim
-
Design and 3D
1 to 3 weeks
Survey, sun study, 3D, proposal
-
Permits
2 to 6 weeks
Plus 2 to 4 weeks if your HOA reviews
-
Gunite build
10 to 14 weeks
On site, after the permit
-
Fiberglass build
4 to 7 weeks
On site, after the permit
The ten stages
Week by week
-
Stage 01 · Week 0
Design consult
We meet at your home, walk the yard, talk about how you will use the pool and give you an honest first range.
-
Stage 02 · 1 to 3 weeks
3D design and proposal
Survey, sun study and a 3D design with two rounds of changes. Then a written proposal with every line priced.
-
Stage 03 · 2 to 6 weeks
Contract, engineering and permits
Engineered plans go to your city (and HOA, which can add 2 to 4 weeks). We handle the forms and the follow-up.
-
Stage 04 · 2 to 5 days
Layout and excavation
We paint the shape on the ground and walk it with you before digging. Rock can add days; you hear about it the same day.
Layout day: the shape is painted on the ground and walked with you before any digging. -
Stage 05 · 1 to 2 weeks
Steel and plumbing
Rebar cage, plumbing lines and electrical bonding. The city inspects before any concrete is placed.
-
Stage 06 · 1 day, then 7 to 10 days
Gunite shoot and cure
The shell is sprayed in one day, then watered daily while it cures. Fiberglass pools are set by crane here instead.
Shoot day: gunite goes on over the steel in a single day. Fiberglass shells are set by crane instead. -
Stage 07 · 2 to 3 weeks
Tile, coping and decking
Waterline tile, coping and the deck. Outdoor living work usually runs at the same time.
-
Stage 08 · 1 to 2 weeks
Equipment, electrical and barrier
Pump, filter, heater and controls are set. Fence, gates and door alarms go in and are inspected.
-
Stage 09 · 2 to 4 days
Interior finish and fill
The finish goes on and the pool fills the same day. Keep the hose running; it takes 1 to 2 days.
-
Stage 10 · 2 weeks
Start-up and pool school
We balance the water, brush the new finish and teach you the equipment, the chemistry and the safety plan.
What slows a build down
No builder controls the weather or the bedrock. What we control is how fast you hear about it. Every delay gets a call the same day and a line in the Friday update.
-
01
Rain
We cannot dig, shoot or pour in heavy rain, and a soaked hole needs time to drain. Expect a few rain days in spring and fall.
-
02
Rock
Limestone is common west of MoPac. It slows digging and is billed at the per-load rate in your contract. You get photos the same day.
-
03
Permit and HOA queues
Some cities turn permits around in two weeks, others in six. HOA boards often meet monthly. We submit the day plans are ready.
-
04
Changes mid-build
Changing the tile or adding a feature is fine, but each change is a written change order with its own price and days.
-
05
Material lead times
Popular fiberglass shells, heaters and some tiles can have waits in spring. We order early and tell you the dates.
-
06
Inspections
Each inspection needs a city slot. Most come within two or three days; we book them as soon as the work is ready.
Decisions, and when they are due
Late choices are the delays we can avoid together. Here is when we will ask.
- Before you sign
- Pool shape, size, depth, features and the barrier plan
- Before excavation
- Equipment location and where the dirt and machines go
- By the end of steel
- Waterline tile, coping and interior finish colors
- Before decking
- Deck material, color and drainage
- Before start-up
- Who in the family attends pool school
The Friday update
Every Friday of your build, Grant sends photos and four lines: what got done, what is next, anything that slipped, and anything we need from you. If nothing happened that week, he says so.
- One superintendent from dig to start-up
- Same-day call for rock, rain or a failed inspection
- Payments due only when a stage is finished
Want a start date you can plan around?
At your design consult we check permit queues for your city and shell stock, then give you an honest window for your first swim.